Showing posts with label Ridley Terminals. Show all posts
Showing posts with label Ridley Terminals. Show all posts

Thursday, January 08, 2009

Reductions in production could see shipment volumes fall at Ridley Terminals


As Western Canadian Coal makes plans to make some changes to its production plans in 2009, the impact on Ridley Terminals could be a sizable reduction in the volume of coal shipped out of the Prince Rupert port.

Western Canadian is reported to be considering reductions in volume to Prince Rupert of 50 per cent as demand for their product declines amid the current uncertainty of the economic climate. Officials at the company are quick to remind people however that all of their plans are contingent on the demand on the world market, which will dictate the amount of product that they will provide in the next twelve months.

The news hasn't for caused much in the way of change for the plans of operation at Ridley Terminals as Chairman Dan Veniez doesn't anticipate any major alterations to operations heading into 2009.

The Daily News outlined the background on the reduction of production and its impact on Ridley as part of the Wednesday paper.

Ridley likely to see coal volume fall
Mining operation will be cutting production but no job impact expected
By George T. Baker
The Daily News
Wednesday, January 07, 2009
Pages one and three

A major customer at Ridley Terminals Inc. is expecting a slower year in demand for coal products and will be almost halving the amount of coal it ships through Prince Rupert.

Western Canadian Coal, which began shipping its low-volatile PCI coal through Ridley in 2007, will be cutting production in two northern mines, the company said Tuesday.

"I emphasize these plans are contingent on what the demand of metallurgical coal will be for the next coal year," said WCC President and CEO John Hogg.

"Whether we reduce operations and to what levels, will depend on the demand for our coal. We hope this will become clearer in the coming months. Until then, we continue to focus on working safely, increasing productivity and lowering costs to remain competitive through these difficult times."

The announcement Tuesday has put a damper on what has otherwise been a solid relationship for Ridley.

Originally, when the Brule mine project began, WCC expected to deliver 800,000 tonnes per year through Ridley but last year the company produced 1.3 million tonnes.

The news comes as another example of how global demand for resources have taken a hit in the last six months.

In November, WCC announced record returns for its 2009-second quarter, where the average realized price of $279 per tonne in the current quarter was 252 per cent higher than the same quarter of 2008.

Reduced operating rates resulted from rising inventory levels as some customers defer shipments through the next few months.

With the current production curtailments taken by some customers, along with the uncertainty of the coal markets beyond April 2009, WCC has made these decisions.

WCC said it expects to operate at these rates until the current economic uncertainty improves and the demand for coal becomes clearer. When the markets do improve, the company has the flexibility to quickly increase operating rates and also pursue its growth plans.

Global demand for coal has weakened since 2007 leaving major coal producers with surplus coal stock instead of surplus profits.

South Africa's Richards Bay Terminals, the world's largest coal exporter, shipped 6.6 per cent less coal in 2008 than 2007.

China, the world's second-largest user of natural resources, has slowed its growth of coal use and expects it only to rise by 4.5 per cent for 2009 from 2008.

Back in Prince Rupert, Ridley Terminals Chairman Dan Veniez said that the coal market can "turn on a dime" and that WCC's announcement was not necessarily unexpected, given current credit crunch.

While he would not go into specifics about the troubles facing WCC, he did say that the ripple effects at Ridley would not create layoffs.

"At this stage, however, we don't anticipate any change in employment levels at RTI, and certainly no changes are even being remotely considered," said Veniez. "We're very proud of the extraordinary productivity and efficiency performance shown by all RTI employees. They've done an incredible job over the past several months. Our costs are under control and our customers are being served extremely well by our workforce at all levels."

Friday, March 14, 2008

Jilted would be Terminal owners to Ottawa: Show Us the money!


Ottawa may be on the hook for a 30 million dollar payout, should a consortium of companies which wanted to purchase Ridley Terminals win their court case over a privatization plan that never happened.

Krisendra Bisetty of Business in Vancouver magazine outlined the moves by the group as they prepare to take their case into B. C. Supreme Court, seeking damages of more than 30 million dollars after the on again, off again sale reached off again status in 2006.

Rupertites will remember that the fate of Ridley Island Terminals became one of the key topics during the last federal election, and it was when the Harper government took office that the planned sale was cancelled. (Podunk passim 1 and Podunk passim 2).

The resurgence of the coal market as outlined in this Daily News article from 2006, is just one example why the consortium is now taking things to another level.

The march to the courts is just the continuation of the always interesting events that have surrounded the Terminal in the last number of years.

The Daily News featured the latest developments in Thursday’s paper.

Would-be buyers of Ridley Terminals seek $30m
By Krisendra Bisetty
Business in Vancouver
March 13, 2008

The Crown is facing a damages claim seeking more than $30 million over the on-off sale of the dry bulk assets of Ridley Terminals Inc.

In papers filed in B. C. Supreme Court, the plaintiffs claim Ottawa backtracked from selling the federal Crown-owned coal facility despite allegedly giving approval expressly or implied, of their binging acquisition proposal.

The plaintiffs, Northwest Bulk Terminals Inc., Federal White Cement Ltd., and Fortune Minerals Ltd.., an Ontario natural resource company with a northwester B. C. coal project that’s in the permitting stage, claim they were the preferred bidder for the assets of the money-losing Crown corporation.

Northwest had offered $20 million for assets that had cost taxpayers approximately $240 million when they were built in 1983.

The planned privatization was initiated in 2002, when the coal industry was still in the doldrums, But the plaintiffs alleged the value of the assets as a going concern was significantly less than its initial cost.

According to their claim, Ridley which is also cited as a defendant, wrote down the value of approximately $25 million in 1990 and by a further $6 million in 2002.

Ridley thereafter received several advances from the Crown to cover cash shortfalls, said the plaintiffs, who added that by Dec. 31, 2006, the corporation had racked up an accumulated deficit of $186.1 million.

As part of court documents, the plaintiffs said they provided access to their confidential business plans for the terminal, including a product diversification strategy.

Things started to turn against them, however, as a result of a delay in finalizing the sale. From 2003 to 2006, the outlook for the coal industry improved, and there was broad expectation that Ridley would see a bigger volume throughput. As well, “political interests” opposed to the sale took steps to “interfere” with their proposal, the plaintiffs claim.

In February 2006, the plaintiffs said they were informed through various sources, including the media, that the Crown planned to discontinue dealing with them.

The Crown later confirmed it would terminate the process for the divestiture of Ridley’s assets.

The plaintiffs claim that amounted to breach of its obligations, ”contractual and otherwise.” They added that the defendants had “wrongly” used their confidential information to develop and implement a modified business plan for Ridley.

Robin Goad, president and CEO of Fortune Minerals, which together with Federal White Cement owns the shares of Northwest Bulk Terminals, said they have yet to hear a response to the action, which includes a damages claim totaling $31,250,000.

In an interview, Goad said that the alleged government about0turn was huge disappointment, “We felt it was a great opportunity that had been overlooked by others,” he said of the coal facility.

“A lot of people had felt that the coal business was dead, and we disagreed. We felt there was a good opportunity there, so it would have been a very lucrative asset for us, and we’re disappointed in the way that the government handled it.”

Ridley’s president and CEO Greg Slocombe, who said the summons had yet to be served, declined to comment on the action, referring inquiries to the federal government.

He said in 2007 the facility, which was built to provide an export point for vast reserves of metallurgical and thermal coal in northeastern B. C., handled 5.1 million tones of commodity, most of which was coal. Ridley also processed wood chips and petroleum coke.

“It always has had a significant value, but it has much better cash flows today than it had a few years ago,” Slocombe said of the Ridley Island facility.

”It’s just the fact that we’ve got volume whereas a couple of years ago, we really didn’t have any activity.
.
Photo above from the Ridley Island website

Wednesday, December 19, 2007

Coal in Dan Veniez’s stocking well past Christmas


The Daily News has what may be the first interview with Dan Veniez since the controversial industrialist was named chair of Ridley Terminals.

Veniez has almost become mythical over the years, thanks to his efforts in the early part of this century to, restructure and resuscitate the Watson Island Pulp Mill. It was an effort that eventually was abandoned due to a lack of financing leaving the mill in bankruptcy and the local economy in a tailspin, twin events that also coincided with a split of the town down any number of directions, like no other issue has in the past.

Veniez reflects back on that era in the article, proclaiming that “thoughtful people” will understand that New Skeena and it’s parent company NWBC “came damn close to getting the mill up and running”, perhaps a statement that not all will agree with.

He returns to the northwest thanks to an appointment from the Conservative Government which named him the Chairman and President of the terminal in a flurry of patronage appointments a few weeks ago.

Veniez in the article, says that he had to think twice before taking the position, and only did so once he was assured that the government had no plans to revive its plans to sell off the Terminal, a still common concern around the community.

His return will certainly prove to be another interesting twist for the Northcoast, and we’re pretty sure that there will be plenty to keep an eye and ear out for once he’s back in the saddle in town.

The Daily News featured the new CEO’s thoughts as part of their front page in Wednesday’s paper.

A controversial figure such as Veniez of course will find more than a few detractors come along the way, thoughtful in their thoughts as well. One of which forwarded his thoughts to the Daily News in a letter to the editor, which we provide following the front page story below.

VENIEZ RELISHING CHANCE TO SHAPE RIDLEY’S FUTURE
Former Skeena CEO returning to North Coast at helm of another big player
By Leanne Ritchie
The Daily News
Wednesday, December 19, 2007
Pages one and three

Dan Veniez admits he had to think twice before agreeing to return to the Northwest.

The former CEO of New Skeena Forest Products, who led a widely publicized attempt to restructure and restart Skeena forestry operations between 2003 and 2005, said he has been busy with new projects since the company declared bankruptcy in 2005.

But the thought of working with a key piece of Canada’s national port infrastructure is what lured him back to the region as the new chair of the board of Ridley Terminals.

“I was asked an initial reaction was ‘No, I’m busy, I am doing a lot of other stuff,” said Veniez.

“And then I was asked again. It’s been a strategic asset for the country and it has been orphaned really, the last three years without a Chairman and CEO and the previous three, it was caught in a bit of a quagmire as far as the future of the place as far as the government of Canada ownership of it.”

In 2005, the Canadian government, then headed by the Liberals, was proposing to sell the terminal to a private company.

Ridley had been losing money for several years following the closure of the last coal mines in the Northwest.

However, industry protested, arguing mining in Northwester B. C. is on the rebound and saying that selling the terminal would create a monopoly on the bulk exports.

And Mike Tarr, former chair of the board of Ridley Terminals and current chair of the Northern Savings Credit Union, argued the terminal was on an economic rebound after successfully diversifying its product line from coal to wood pellets and potential sulphur shipments in the future.

The sale became a dominant election issue in the winter of 2005 and one of the first things the Conservative government did after being elected in early 2006 was to cancel the sale.

After being assured that the government had no intention of reviving any attempts to sell it, Veniez agreed to fill the role of board chair, a role that has been vacant since Tarr left two years ago.

“It’s an important asset in Canada and the government of Canada feels it’s a critical link in a broader gateway strategy.

I’ve been pretty heavily involved in other important parts of the economy in the last several years and I can tell you, the economic pull coming out of Asia is as strong as anyone has ever seen it and Ridley could and should be diversifying it product mix and its supplier mix to really take advantage of that asset,” said Veniez.

“It’s been functioning under-capacity for years and in part that’s a function of the general state of the global economy and in part its other things too. I will help Greg Slocombe, Chief Financial Officer,) and the team put this on the map from a business perspective and make sure Ridley’s interests are at the top of mind in Ottawa.”

Veniez acknowledges there are people in the Northwest who do not like the way he handled the efforts to restructure new Skeena, however those who are thoughtful and those he respects understand that he, and George Petty, president of New Skeena’s parent company NWBC Timber and Pulp, put every effort in to making it work, he said.

“The view from thoughtful people is that if we couldn’t get it up and running again, no one could. That’s exactly what happened. We came damn close and thoughtful people know it,” said Veniez.

“We were always very, very straight with people and in business that means a lot.”

Since New Skeena Forest Products declared bankruptcy in 2005, the company was sold in pieces – The Terrace sawmill was bought and restarted by a group of Terrace businessmen and has since gone belly up; the Watson Island Pulp mill is in the hands of Sun Wave Forest Products, a Chinese government-owned company, however there is no indication of a restart any time soon because Watson Island property is being leased for use by several businesses, including the new Container Examination Facility for the Fairview Container Terminal; and the forest licences have been sold to local First Nations, with the largest assets in the hands of the Lax Kw’alaams and Gitxsan.

Shortly after the bankruptcy of new Skeena, George Petty, a man known for more than three decades of work rebuilding mills across Canada, died from complications arising from kidney transplant surgery.

The 72 year old passed away peacefully in Key West, Florida.

Since then, Veniez has been working as a partner for the Centre for Executive Development, is chairman of DDV Enterprises Ltd., an investment company, and is an operating advisor to Pegasus Capital Advisors, a private equity group that manages more than $1.8 billion (U. S) in assets through several funds.

He will be meeting in the near future with the terminal’s management team and said he is looking forward to working with them.

LETTERS TO THE EDITOR
The Prince Rupert Daily News
Wednesday, December 19, 2007
Page 4

To the editor,

Unfreakin’ believable!

After the fiasco that Mr. Dan Veniez dragged this community through during his “alleged” attempt to make the pulp mill a viable operation again, the federal government, in particular the Honourable Mr. Lawrence Cannon, has appointed Mr.Veniez as chairperson of the Ridley Terminals Inc. board of directors.

One wonders if the government checked (or even cared) about history in this community.

In any case, this is, in effect, a slap in the face to this community in general, and all those families in particular who suffered during his previous involvement in our community.

If I sound pissed off, I am.

Yours Truly,
Jim Trerise

Thursday, May 31, 2007

Ridley Terminals adds Pellets to the shipment mix


Wood pellets are now being shipped out of the Port of Prince Rupert, as Ridley Terminals exported the first load of pellets on Sunday. It’s a new addition to the shipment mix on Ridley Island and one that could expand quite quickly in the years to come.

The Daily News provided a review of the project and a look down the road in Tuesday’s paper.

PELLETS ADD NEW STRING TO RIDLEY’S BOW
By Leanne Ritchie
The Daily News
Tuesday, May 29, 2007
Page one

On Sunday, Ridley Terminals shipped out its first load of wood pellets from Houtson Pellet Inc., marking the beginning of another new product being handled at the terminal.

Greg Slocombe, CEO of the bulk handling facility, said he believes this is the beginning of very good partnership.

“This is a brand new business and we think we are on the right end,” said Slocombe. “There is huge opportunity on the supply side in British Columbia.”

The pine beetle epidemic in the Interior is causing elevated harvesting levels as forestry companies rush to bring in the timber before it is completely useless.

While the wood pellets from Houston Pellet Inc. are manufactured from a byproduct of wood being put through a mill, the rush to harvest wood from the Interior could result in additional wood pellet production.

“Two or three years from now we may see them harvesting trees just to make pellets,” said Slocombe. “We are in at the right end.”

Slocombe believes it could go from a 100,000 tonne business annually to 1.1 million tones business in five years.

Houston Pellet is a partnership of Canadian Forest Products (Canfor), Pinnacle Pellet and the Moricetown First Nations. The 6mm pellets are manufactured from planer shavings and sawdust from the Canfor Houston sawmill. The pellets will be sold both overseas and into the domestic pellet market for home heating.

CN Rail is transporting the pellets from Houston to Ridley, where they will be stored in a 105-metre wide silo and loaded onto ships able to hold 8,000 to 9,000 metric tones.

The first shipment is destined for the Netherlands and from there will be transported to Belgium.

Ridley Terminals is operating the new loading facility that was built by Houston Pellet.

Ridley Terminals, a federally-owned corporation, has struggled financially and has only recently begun operating without government assistance.

Partnerships such as this give the terminal the opportunity to continue to diversify the products it handles and provides stability for the long term from the ups and downs of the coal market.

“We are having to share the benefits but we are tied in with an excellent company,” he said. And the arrangement between the companies is structured so other small operators can move their product through Ridley.

The new equipment at the terminal to handle wood pellets includes a pellet rail car unloading building, rail car hopper gate opening equipment, a pellet unloading conveyor designed to move the pellets to the storage silo, the pellet storage silo itself, and a pellet silo unloading conveyor that goes out to the ship.

Wednesday, April 25, 2007

Labour woes work in Rupert’s favour


Two separate sets of labour difficulties are making the Port of Prince Rupert a desired location to send product these days.

The recent CN strike and a retaliatory lock out of Vancouver based rail workers, is combining with a potential strike at CP Rail to drive more business towards athe northwest and the Port of Prince Rupert.

Add in the fact that the CN dispute has resulted in a perceived congestion problem at the Port of Vancouver (one the Port there is struggling to explain as non existent) and suddenly the Port of Prince Rupert is a destination for shippers looking to move their product as expeditiously as possible.

The Vancouver Sun had an interesting look at how the Northwest corridor is finally starting to get the message across that it’s a reliable, quick and hassle free way to get product to consumers.

Rupert stands to gain from labour strife
Railway work stoppages mean northern port starting to see more work
Fiona Anderson
Vancouver Sun
Wednesday, April 25, 2007


The Port of Prince Rupert may be the ultimate beneficiaries of work stoppages like the recent CN Rail strike-turned-lockout and a threatened strike of maintenance workers at Canadian Pacific Railway Ltd.

Legislation ordered CN Rail conductors and yard workers back on the job on Thursday. But Prince Rupert was "happily" unaffected by the job action which lasted just over a week, said Greg Slocombe, president and chief operating officer of Ridley Terminals Inc. in Prince Rupert.

The United Transportation Union initiated what were to be rotating strikes on April 10 after almost 80 per cent of their members who voted rejected a tentative agreement with the Canadian National Railway Co. CN then retaliated by locking out the employees who had gone on strike.

"Fortunately for us [the UTU] started its rotating strikes where there would be highest impact and that's Vancouver," Slocombe said. "So they locked them out down there. But we've not seen any job action up here at all so therefore there's not been lockouts."

And as CP doesn't have a rail line to Prince Rupert, a threatened strike by the 3,000 maintenance-of-way employees represented by the Teamsters Canada Rail Conference will also have no negative effect.

And in fact, both work stoppages could actually benefit the northern port.

"In a back-handed way, because they've had some challenges in Vancouver, not necessarily just strike-related but congestion related [as well], that's actually playing into our hands," Slocombe said. "It's starting to throw more business our way."

Ridley, which is a bulk coal terminal, expects its shipments to at least double this year, partly due to increased production in northeastern British Columbia, and partly due to congestion in Vancouver-area ports.

Jeff Burghardt, president of Prince Rupert Grain Ltd., which handles wheat, durum, barley and canola, said his company didn't notice any increase in shipments due specifically to the CN dispute. But Burghardt is finding more and more customers want to do business out of Prince Rupert.

"I think there has been a gradual recognition that the northwest corridor [through] Prince Rupert can deliver superior service and people are certainly recognizing the value of more reliable delivery times," Burghardt said. "And that's helping us."

Total grain shipments from the West Coast is expected to be 16 to 17 million tonnes this year, up from a five-year average of 13 million tonnes.
"A lot of that incremental business is finding its way exclusively to Prince Rupert," Burghardt said.

Denis Horgan, vice-president and general manager of Westshore Terminals, which handles coal in the Lower Mainland, said that since January the terminal has lost two or three ships to Ridley in Prince Rupert.

A number of factors contributed, including the CN lockout and bad weather. But CN has been promoting Ridley "as a less-congested option," Horgan said. The congestion is on the railroad, not at the terminal, which last year moved 19 million tonnes of coal but has capacity for 24 million tonnes increasing to 29 million tonnes, Horgan said.

"There's no congestion here. We've lots of capacity. But certainly for whatever reason CN would seem to prefer the Ridley gateway over the Vancouver gateway for coal because of congestion or perceived congestion in the Vancouver rail corridor," he said.

"We're not congested or over capacity," he added. "We'd certainly like to be, but we're not."
Scott Galloway, director of trade development at the Vancouver Port Authority agreed that capacity was not the issue.

The port only looks at numbers annually, so Galloway couldn't say if there have been any shifts away from Vancouver to Prince Rupert so far this year. But last year, the port set a record for tonnage, he said.

"And I would still argue that there is a lot of capacity left on the bulk side and the container side," Galloway said.

Tuesday, April 03, 2007

Sulphur plans revisited on Ridley Island

The nearly completed sulphur terminal on Ridley Island may soon find a second life, though not quite in the same form as the original design laid out.

Ridley Terminals and ICEC Terminals have begun their environmental work on the site that could lead to the shipment of sulphur through Ridley Island by 2008 and provide employment for 8-10 residents of the area.

The revised plan for the incomplete terminal was outlined in Monday’s Daily News.

SULPHUR IS FINALLY ABOUT TO FLOW THROUGH RIDLEY
Expected to handle 800,000 tonnes a year and provide eight to 10 jobsBy James Vassallo
The Daily News
Monday, April 2, 2007
Pages one and three

Ridley Terminals and ICEC Terminals have begun the environmental assessment process that could see the companies develop the sulphur terminal that was abandoned in 2001.

According to the environmental assessment report, ICEC is planning to complete construction and operate a portion of the sulphur terminal by leasing the incomplete facility from Ridley Terminals.

“The general concept involves receiving molten sulphur by rail cars, unloading railcars into a liquid sulphur storage pit, forming the liquid sulphur into dry bulk form, then stockpiling and loading the dry bulk sulphur onto ocean vessels for export to overseas markets,” reads the report.

The facility will be designed to handle 800,000 tonnes per year, potentially expanding to 1.4 million tonnes per year.

“The project design is environmentally sensitive to minimize fugitive dust, sulphur compound vapor emissions and cross contamination with other bulk products.”

ICEC acts as a international marketer of fertilizer and fertilizer raw materials and has some 20 offices around the globe, with major operations in Crossfield, Alberta; Brazil and Tengiz, Kzakhastan.

Vessels would e expected to pick up sulphur from Ridley Terminals every 35 days.

Unlike the previous owners of the facility, ICEC has no plans to use the liquid storage tanks and liquid loading system, but will move all the product in its dry form.

Although sulphur vapours will be created when the sulphur is heated to get it out of the rail cars, there is not expected to be any smell because the vapours will be collected and put through a scrubbing system that will remove the sulphur compounds before the air is vented into the atmosphere.

ICEC and Ridley Terminals met this January with the District of Port Edward to describe the project and talk about potential concerns.

“Port Edward was interested in the employment opportunities and did not express any other concerns with the proposed project,” reads the report.

“They were happy to see project development occurring in the region,” reads the report. They also met with Prince Rupert Mayor Herb Pond who expressed similar feelings.

The new facility is expected to create eight to ten new jobs at Ridley Terminals.

“The design of this facility will incorporate current industry standards and be a state of the art world-class facility,” reads the report.

The company is expected to put out a “request for proposals for a contractor to build the new components some time in early summer, with operations set to commence in 2008.

The $60 million sulphur facility at Ridley was a project of the Sulphur Corporation of Canada (SCC). It was started in 2001, however it was never completed and the project was eventually handed over to Ridley Terminals/

SCC was planning on handling both liquid sulphur, which would be stored in large storage tanks as well as formed sulphur, similar to the solid product now exported from the port of Vancouver.

However, the project was derailed after SCC filed for bankruptcy protection. It owed $29 million in debt, some of which was owned to Prince Rupert contractors.

Wednesday, February 14, 2007

Late February delivery for first shipment of Brule Mine Coal

The Port of Prince Rupert is looking forward to the arrival of coal from the Brule Mine project in late February, product that is destined to ship out of Ridley Terminals. The mine located in Northeastern British Columbia is run by Western Canadian Coal and the company is expecting great success from its mining ventures there as the demand for the coal being produced is exceeding the supply, commitments for all of the expected production is now accounted for.

This will add throughput volumes to Ridley Terminals which has seen an increase in shipping from the terminal in the last year.

The Daily News had an in depth look at the mining project and its impact on Prince Rupert in Tuesday’s paper.

NEW MINE ANOTHER BOOST FO RIDLEY
By Leanne Ritchie
The Daily News
Tuesday, February 13, 2007
Page one


Western Canadian Coal, a mining company with properties in Northeastern B. C., has received approval to open a new mine.

Gary K. Livingstone, president and CEO of Western Canadian Coal (WCC), said the company recently received approval to start up its Brule Mine, which will replace production at the Dillon Mine, a 1.3 million tonne mine that is now depleted.

Mining at the Brule Mine commenced in January 2007 and the first vessel taking PCI coal from Brule is expected to depart Ridley Terminals in Prince Rupert later in February.

“With current demand for the Burns River PCI coal exceeding supply, the company has commitments from its customers covering all of the Brule Mine’s expected production,” said Livingstone.

Production at the Brule Mine will be approximately 800,000 tonnes of PCI coal per year.

The company ships all of its product from Northeaster B. C. by rail through Ridley Terminals to overseas markets.

Meanwhile, it is anticipated that of the 1.0 million tonnes of coking coal produced in the current fiscal year, approximately 900,000 tonnes will be shipped prior to March 31, 2007, representing all available production except that portion required to maintain adequate mine and port inventories.

“Despite the slower than expected ramp up at the Perry Creek mine and delays by some customers in completing the testing required to determine the product’s suitability, more than 578,000 tonnes of Wolverine hard coking coal has been shipped to customers through January 2007 and the company has secured coal supply agreements for its Wolverine hard coking coal in Asia, Europe, South America and India,” said Livingstone.

“The company has recently secured large volume sales commitments to major Asian steel mills and a European mill for coal year 2007 (fiscal year 2008) and negotiations are ongoing to secure additional Wolverine hard coking coal contracts with steel mills both in new and existing markets.

“Efforts are being made to seek new customers in North and South America, as well as in Eastern Europe and the Middle East. The company anticipates this will result in more than a doubling of sales volumes for Wolverine coal in the fiscal year ending March 31, 2008 to between 2.2 – 2.4 million tonnes.”

Livingstone notices that coal prices are down a bit for 2007, the largest metallurgical coal exporters settled their coal pricing in Japan and Korea for the 2007 coal year, down US$18- $20 per tonne, at between US$98-$70 per tonne with Wolverine equivalent quality coals selling in the US$94-85 per tonne range.

While the other major steel mills have not completed their 2007 coal year settlements, the company believes that the final price settlements will not be materially different from these initial settlements.

Pricing of ULV-PCI for the upcoming coal and fiscal year is expected to remain in the high US$60s per tonne.

Monday, December 04, 2006

Expansion of Ridley Island facilities won’t have a negative impact on Port Edward

Concerns by Port Edward officials over the introduction of a wood pellet facility to Ridley Island were addressed by Terminal representatives last week, who stressed that the loading and storage facility would not have a negative impact on the town.

With a plan for up to five silos to be built, the plan is to export the wood pellets to overseas destinations mainly in the Asian marketplace. Bill Myers the human resources and loss control coordinator at Ridley Terminals Inc. addressed the issue with Port Ed Council who were concerned about dust from the product wafting over to their town.

Myers said that in windy or rainy conditions the silos would not run, which leaves many in the area scratching their heads, wondering exactly when the terminal would operate considering our rather unpredictable climate, which frequently features the rain and the wind. It might be a pretty small window of opportunity following that guideline for shipment.

The full story of the latest addition to the economic scene was detailed in the Thursday edition of the Daily News.


RIDLEY’S PELLET PROJECT EXCITES COUNCIL
By Patrick Witwicki
The Daily News
Thursday, November 30, 2006
Page one


Port Edward residents will not be negatively impacted by the new Ridley Island Pellet Ship Loading facility, said Bill Myers, human resources and loss control coordinator, Ridley Terminals Inc.

Myers attended Port Edward council Tuesday night, and outlined the five year plan that will enable Ridley Terminals to ship wood pellets overseas, after transporting the pellets in from a sawmill in Houston.

“Silos will be built for the next five years,” he said. “(Our hope is for) five at the end of the project.”

The plan is to build one silo at a time, to provide a conveyor belt that will connect grain cars, to dumpster, to ships to transport the pellets overseas, especially in the growing Asian market.

Once the silo’s are in place, Ridley Terminals will be able to handle up to six rail cars a day, and unload 500 metric tones per hour, said Myers.

Then, the pellets will be transferred via conveyor from the off-loading station to the top of the silo, before being transferred to the main tank that can hold 11,000 metric tonnes of pellets. From there, the pellets eventually get transferred to ships. Some 2,000 metric tones will be dispensed per hour, he said. It’s expected that each vessel will be able to bundle up to 9,000 tonnes.

The District of Port Edward was concerned about the impact from construction, and subsequently, dust from the actual wood pellets. But Myers said that the entire project is adhering to strict environmental guidelines, and shouldn’t impact the community.

“(The dust) will be screened twice at Houston, and once at Ridley,” he said.

In windy or rainy conditions, the silos won’t run. “We don’t want to get the pellets wet,” he said.

In regards to the construction, he said that the steel has just arrived.

“They’re putting in the forms for a 12 foot wall,” he said.

After the first silo is complete, the plan is to build four more. The Houston sawmill is taking advantage of the wood-beetle decimated wood, and providing overseas markets with an alternative method to burning fuel.

“What they’re starting to do (over in Asia) is experimenting with coal and pellets,” said Myers. “If you burn a biofuel, you get credits for that. There’s a huge market for this,”

The expansion at Ridley Terminals is also expected to help both Port Edward and Prince Rupert economically, said Myers.

“In the first year, we’ll be able to handle it ourselves,” he said. But as the business expands, we’ll be looking at hiring, (Currently,) we’re looking for trades people who have operating experience.”

Coun. Murray Kristoff summed up the positive feeling for the entire district by saying, “It’s nice to see something happening out at Ridley.”